Requirements for the material are different between different regions, this guide illustrates how to show the requirements in spaces/rooms.


Firstly make sure that spaces have FireReq_RectionFire parameters. Go to Manage -> Project Parameters and check.


Select the space and enter all material requirement


Make sure to communicate with the other stakeholders that it's possible to check materials toward the space requirement.

Depending on how much information is entered on the spaces, it's possible to have an internal quality check of the requirements either using a color scheme or a space tag. 


Using color scheme to color one parameter at the time,


Or to showcase all FireReq_ReactionFire parameters, use attached space tag. The tag uses Swedish for now, contact the BFT team to have a local variant of it.



----------------------------------------------------------------------------

In the Architect model, make sure that FireReq_ReactionFire... is loaded, read more. In a floor plan, open a floor plan and enable a color scheme for spaces, make sure include elements from links are ticked.